Author Mark Watson
Houston — Almost 5.9 GW of generation is under construction in the Midcontinent Independent System Operator footprint with negotiated in-service dates before the end of 2020, a report generated July 6 shows, and that excludes 489 MW of gas-fired generation that Entergy plans to bring online in 2020.
The MISO Generation Interconnection Queue status report only includes one natural gas project, the 705-MW project under construction to connect to Northern Indiana Public Service in St. Joseph County, Indiana, which remains under construction despite having a …