Author Mark Watson
Houston — The Midcontinent Independent System Operator has so far placed 1,157 MW of new generation into service this year, almost all natural gas-fired, and it has another 2.8 GW under construction to be finished in the remainder of 2019, an interconnection status report compiled Tuesday shows. …