ERCOT gives update on weatherization, but staffing shortages could impact future reliability deadlines

by: Maggie Glynn

AUSTIN (Nexstar) — On Monday, ahead of the Electric Reliability Council of Texas’ deadline to submit its final weatherization & inspection report Tuesday, the council briefed the new board of directors on weatherization progress so far.

“We found 10 potential deficiencies at dispatchable generation sites. We didn’t find any at the intermittent renewable resource sites. We found six at the transmission service providers facilities,” weatherization and inspection director David Kezell outlined.

Those generators will all be …